Date initiated & completed: 2016
PROJECT DESCRIPTION
In 2016, SAR played a crucial role in restructuring the routing
of the BMW paint shop’s 7-meter-level body routing. This
project was carefully planned to minimize disruption to
production, avoiding the need for any shutdown periods during
installation.
By breaking down the project into distinct steps, we were able
to execute it incrementally over weekends. This ensured that
each phase of the restructuring could be completed weekend
by weekend, ultimately creating the successful implementation
of the new routing system without interrupting ongoing
production operations.
The project expanded over most of 2016 due to the weekend
approach.
TECHNOLOGIES
▪ CONVEYOR TECHNOLOGY
▪ SIEMENS SOFTWARE TIA AND S7
▪ ROLLER BED
▪ SHUTTLES
▪ TURN TABLES
▪ HOISTS
▪ TILTING STATIONS