Date executed: December 2023
PROJECT DESCRIPTION
In December 2023, following the Chassis to Body marriage
process, a critical operation involving the fastening of multiple
bolts in the underbody area of the vehicle was identified. At
Station 56, two operators utilized Atlas Copco bolting tools,
manipulated on telescopic arms, to fasten these bolts
manually, requiring precise positioning for each bolt.
To streamline and enhance this process, an enclosed cell was
installed featuring a split roller bed and two robots,
designated as Robot 1 and Robot 2. Positioned on either side
of the conveyor, these robots are purposed to automate the
bolt fastening task, improving efficiency and consistency while
minimizing manual labor and potential errors.






TECHNOLOGIES
PLC/ROBOT TECHNOLOGY
▪ KUKA V KRC
▪ SIEMENS TIA
BOLTING TECHNOLOGY
▪ ATLAS COPCO
CONVEYOR TECHNOLOGY
▪ ROLLER BED SYSTEM